Polynomial Algorithm for Constructing Pareto-Optimal Schedules for Problem 1∣<em>r</em><sub>j</sub>∣<em>L</em><sub>max</sub>,<em>C</em><sub>max</sub>

In this chapter, we consider the single machine scheduling problem with given release dates, processing times, and due dates with two objective functions. The first one is to minimize the maximum lateness, that is, maximum difference between each job due date and its actual completion time. The seco...

Descripción completa

Guardado en:
Detalles Bibliográficos
Autores principales: Lazarev, Alexander A., Pravdivets, Nikolay
Formato: Capítulo de libro
Lenguaje:inglés
Publicado: IntechOpen 2020
Materias:
Acceso en línea:https://www.intechopen.com/chapters/73530
Etiquetas: Agregar Etiqueta
Sin Etiquetas, Sea el primero en etiquetar este registro!
Descripción
Sumario:In this chapter, we consider the single machine scheduling problem with given release dates, processing times, and due dates with two objective functions. The first one is to minimize the maximum lateness, that is, maximum difference between each job due date and its actual completion time. The second one is to minimize the maximum completion time, that is, to complete all the jobs as soon as possible. The problem is NP-hard in the strong sense. We provide a polynomial time algorithm for constructing a Pareto-optimal set of schedules on criteria of maximum lateness and maximum completion time, that is, problem 1 ∣ r j ∣ L max , C max , for the subcase of the problem: d 1 ≤ d 2 ≤ … ≤ d n ; d 1 − r 1 − p 1 ≥ d 2 − r 2 − p 2 ≥ … ≥ d n − r n − p n .
ISBN:978-1-78984-718-5
DOI:10.5772/intechopen.93677